🌐 Connectivity for commercial and industrial consumers
🧩Why Connectivity is precious for C&I Consumers
Planning for renewables is half the story for commercial and industrial consumers . The other half is having a approval for connectivity including state transmission general network access. ( GNA as it is being called commonly) The reason why big developers like Renew , Azure , Avaada have exited (or not been successful ) in the commercial and industrial market , while small agile developers are , is because of connectivity approval. The mose agile developers are the ones who have connectivity ready.
For Commercial & Industrial (C&I) consumers aiming to secure reliable 24x7 renewable power ( not just only solar / wind ) at a competitive rate (₹5/unit- (₹6/unit-), connectivity to the transmission network is the first and most important puzzle piece. Here's why:
✅ The Challenge
-
C&I consumers increasingly demand 24x7 clean power, not just solar during the day.
-
Many need complex PPAs that combine solar, wind, and storage, often across states.
-
However, current models like LTA (Long-Term Open Access) , MTOA ( Medium-Term Open Access) , and STOA (Short-Term Open Access) limit flexibility and often don’t guarantee new transmission infrastructure.
-
DISCOMs are hesitant to sign long-term PPAs, leading to a rise in short-term, unpredictable power market behavior.
🔌 The Connectivity Solution
| Element | Long term or short term open acess (Old model )
|
General Network access (GNA) model
(New)
| | --- | --- | --- | | Access Type | Fixed point-to-point | Dynamic, pan-network access | | Flexibility | Low | High (contracts of varying duration) | | Infra Creation | Not guaranteed | Driven by actual usage & planning | | PPA Fit | Simple solar/wind | Complex 24x7 PPA support | | DISCOM Dependency | High | Lower, enables open access | | State RE Transactions | Mostly intra-state | Inter-state possible if aligned with CERC |
Here’s a simple 1-slide style explainer for:
⚡️ Does GNA Cover STU? ❌ No — and Here’s Why It Matters
✅ What GNA Includes:
-
Issued by CTUIL
-
Grants right to use the Inter-State Transmission System (ISTS)
-
Includes:
-
Injection validation (by CTUIL)
-
Intermediate ISTS corridors
-
Point of drawal (up to state periphery)
-
🚫 What GNA Does Not Cover:
-
State Transmission Utility (STU) Network
-
Intrastate lines (e.g., from Delhi periphery to DMRC station)
-
Local STU substation capacity
-
STU wheeling or scheduling
-
🧭 What You Still Need (If You're a Consumer Like DMRC):
-
STU Coordination
→ For physical drawal at your substation (must be cleared by SLDC/STU) -
Separate Charges
→ STU wheeling charges, losses, scheduling fees -
SLDC Confirmation
→ For real-time scheduling and availability
📌 Bottom Line:
GNA gives you a highway pass — but you still need a local road permit.
GNA ensures national grid access, but STU access is still your responsibility.
🌐 How We Can Help
We offer full-stack support to help C&I consumers unlock value from the new model:
| Need | Our Support |
|---|---|
| Connectivity & GNA Access | Assist in securing connectivity & navigating Model State Regulations. |
| Developer Matching | Match with credible developers who can offer bundled solar + wind + storage |
| Solar Park Access | Identify park locations and facilitate plug-and-play entry |
| PPA Structuring | Support in complex 24x7 PPA design, pricing, and risk allocation |
| Funding Access | Connect to green funds & financiers willing to support decarbonization goals |
⚡ PPA with Connectivity
📩 Reach out to [email protected]
🏢 Connectivity approval ready in major India states through our partners.
✴️ KNOW MORE
Eligibility conditions for Connectivity
CERC GNA Regulation | State Open Access Regulations | Comments from Stakeholders | Draft Model State GNA Regulations | Rationale |
Generating Station incl. REGS with or without ESS- 50 MW Captive- 50 MW and above Standalone ESS- 50 MW and above EE Park Developer REGS or standalone ESS- 5 MW and above | MAH: TOA: Consumer ≥ 5 MW Generator capacity ≥ 5 MW DOA: Generating Station < 5 MW TN: Consumer contract demand ≥ 10 MW and Generating Station ≥ 15 MW DOA: Consumer contract demand< 10 MW and Generating Station < 15 MW Gujarat: For InSTS: - Consumers with a load of 4 MW and above and Generators 4 MW and above. For Distribution System: - Generators with an installed capacity below 4 MW. | UP Add seeking connectivity at a single inter-connection point at voltage 33 kV and above” in each point of eligibility. Add distribution licensee Karnataka: Include consumer to apply for connectivity since consumer is eligible in GNA Recommend to delete “Consumer with contract demand 10 MW and above ”if consumer is eligible for connectivity then regulation 5 shall be modified to accommodate the consumer AP: Minimum capacity at different voltage level should be specified | Generating Station incl. REGS with or without ESS and Captive Gen- 5 MW and above. RE Park Developer- 5 MW REGS or standalone ESS- 5 MW and above Bulk Consumer with Contract Demand [5] MW and above or Data Centres operating as a distribution licensee connected to InSTS | Align with CERC and State specific changes in minimum capacity connected to InSTS Network. Added Bulk Consumer with Contract Demand [5] MW and above or Data Center park operating as a distribution licensees |
Application Fees for Connectivity
CERC GNA Regulation | State OA Regulation | Comments from Stakeholders | Draft Model State GNA Regulations | Rationale |
Rs. 5 Lakh for Connectivity by Generators | MAH: Non - RE Gen: Rs. 2.00 Lakh RE Generators: Rs. 1.00 Lakh TN: Transmission Related Upto 100 MW: Rs. 2 Lakh >100 MW and up to 500 MW: Rs. 3 Lakh > 500 MW and up to 1000 MW : Rs. 6 Lakh >1000 MW : Rs. 9 Lakh TN: Distribution: Rs. 1.00 lakh MP: Rs. 1.00 Lakh Gujarat: Up to 100 MW: ₹2 lakh >100 MW and up to 500 MW: ₹3 lakh > 500 MW and up to 1000 MW: ₹6 lakh >1000 MW: ₹9 lakh | UP: Application fee of Rs.1 lakh for distribution along with applicable taxes on application fee. Karnataka: Application fees for Connectivity shall be Rs. 5 Lakh for each. AP Suggested Connectivity fees as Rs. 2 Lakh upto 10 MW, Rs. 4 Lakh (for 10 MW to 50 MW), Rs. 5 Lakh (for 50 MW to 100 MW), Rs, 6 Lakh (for 100 MW to 500 MW), Rs. 9 Lakh (>500 MW). | Application Fees for connectivity by Generators: Rs. 1 Lakh | Rationalization of Application fees and to reduce the initial burden |
Application Fees for GNA by Consumers/ DISCOM
CERC GNA Regulation | State OA Regulation | Comments from Stakeholders | Draft State Model Regulation | Rationale |
Rs. 5 Lakh for GNA application | Karnataka:
MP:
Rajasthan:
Gujarat:
Maharashtra:
|
| Application Fees for GNA: Rs. 1 Lakh (Distribution Entities) Rs. 0.5 Lakh (for entities other than distribution licensees)
| Rationalization of Application fees and to reduce the initial burden |
Send us a email at [email protected].
We will connect you to C&I developer with connectivity who can install solar C&I on your rooftop for INR 3-4/ unit and give you 24X7 energy at INR 5 / unit
Bank Guarantee (BGs) provisions
Eligibility condition for GNA by Drawee Entity (DISCOM/OA user)
Duration of Open Access / GNA
Relinquishment of GNA /T-GNA
Operationalisation of Connectivity conditions
Conditions for Transfer of Connectivity
Connectivity Agreement
GNA Availability and Transmission Capacity Right
Deemed GNA and TCR
Eligibility for Temporary (T-GNA) and short-term OA
Nodal Agency and processing
Commercial aspects of GNA/T-GNA implementation
Eligibility condition for GNA by Drawee Entity (DISCOM/OA user)
CERC GNA Regulation | State OA Regulation | Comments from Stakeholders | Draft State Model Regulation | Remarks |
- STU on behalf of InSTS - Drawee entity connected to InSTS -Distribution licensee or Bulk Consumer with 50 MW or more load -Trading licensee engaged in Cross Border -Transmission licensee connected to ISTS Entities which are connected to the ISTS or for whom Connectivity granted | MAH: Distribution Licensee, Trading Licensee, Consumer Contract Demand of 1MVA and above TN: Licensees, captive generating plants and consumers Karnataka: Allowed OA to consumers in Phases wise (based on CD and voltage level) Madhya Pradesh: Licensees, Trading Licensee, Consumers Rajasthan: Licensees, Consumers, Distribution licensees Gujarat: Licensees, captive plants, and consumers | UP A drawee entity incl. OA consumer and captive user connected to InSTS An injecting entity which is granted Connectivity to InSTS and seeking GNA for injection into ISTS. Suggested to delete: Trading Licensees, bulk consumer, consumers with contract demand 10MW and above, GNA Grantee also eligible for T-GNA Karnataka: In Bulk Consumer- Need to specify capacity limit? Instead of captive consumer, “captive generating plant” to be added GNA Grantee also eligible AP: The meaning for Bulk Consumer shall be specified. | Distribution Licensees A drawee entity including Bulk Consumer or Captive Consumer with demand [5] MW and above connected to InSTS subject to it’s contract demand Intra state entity with drawal of auxiliary power Standalone ESS, REGS for drawal during non-generation hours | Align with CERC and State specific changes in minimum capacity connected to InSTS Network Capacity for Bulk consumer [CD of 5 MW ] aligned with Supply Code requirements. |
Connectivity Agreement
Particulars | CERC GNA Regulation | Comments from Stakeholders | Draft State Model Regulation | Rationale |
Connectivity Agreement | Signed between the CTU and the entity which has final grant of connectivity. (Bi-party Agreement) | UP Suggested to delete tripartite agreement and instead of that Suggested Provision for Connectivity agreement as agreement between the following entities: Applicant & STU: If connectivity is granted to the Applicant with STU's transmission system. STU & Intra-State Transmission Licensee: If the connectivity involves the transmission system of an intra-state transmission licensee connecting to STU's system. Applicant, STU & Other Licensees: If connectivity is granted to the Applicant with a transmission system owned by a licensee other than the STU | Connectivity Grantee, STU and Intra-State Transmission Licensee shall sign a tripartite Connection Agreement (Tri-Party agreement as per existing State OA Regulations provisions ) | Retained Tripartite Connection Agreement |